menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Construction Project Management
  4. Exam
    Exam 4: Project Delivery Methods
  5. Question
    In a Pure Construction Management Approach the Construction Manager Usually
Solved

In a Pure Construction Management Approach the Construction Manager Usually

Question 6

Question 6

True/False

In a pure construction management approach the construction manager usually guarantees the overall price of the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: An advantage of the design/build approach is

Q2: Historically, a "master builder" was hired to

Q3: A unit-price contract provides an owner with

Q4: In a guaranteed maximum price (GMP) contract,

Q5: A project is rushed into design without

Q7: When assessing the risks applicable to a

Q8: The term fast track--------<br>A) Is synonymous with

Q9: The choice of which delivery method is

Q10: In which of the following project approaches

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines