A project is rushed into design without a total understanding of the owner's needs. As the project moves through the design, additional requirements are added, increasing the project budget. This is an example of ????
A) Project acceleration
B) Fast tracking
C) Scope creep
D) Separated functions
E) None of the above
Correct Answer: