Essay
A work cell is required to make 140 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours is available for productive work. These assemblies require five operations. Standard times for these operations are: Operation A, 3.0 minutes, B, 1.8 minutes, C, 2.4 minutes, D, 2.5 minutes, and E, 1.4 minutes. What is takt time for this cell?
How many workers will be needed to achieve this schedule?
Use the grid below to construct a work balance chart for this cell.
Correct Answer:

Verified
Takt time = 420 / 140 = 3 minutes/unit. ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: Four hundred and eighty minutes of production
Q68: Which type of layout is specifically designed
Q71: Explain what the purpose of assembly line
Q72: Cross-docking is<br>A) seldomly placing an item in
Q74: Briefly explain what "slotting" is. Why is
Q76: _ are fees manufacturers pay to get
Q78: A manufacturing work cell has a takt
Q84: Identify McDonald's seven major innovations.
Q223: A big advantage of a process-oriented layout
Q224: A process-oriented layout is the traditional way