    A Task Has a Normal Duration of 9 Days and a Crash
Solved

A Task Has a Normal Duration of 9 Days and a Crash

Question 64

Question 64

Multiple Choice

A task has a normal duration of 9 days and a crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?


A) $140
B) $70
C) $50
D) $40
E) $30

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18: William, a project manager, is trying to

Q21: What is fast-tracking a project?

Q32: Pools of like resources from which labor

Q41: The shortest duration task first rule minimizes

Q49: What is the student syndrome? In what

Q58: Explain how the commonly made assumption of

Q71: Why are scarce resources referred to as

Q73: A limitation associated with traditional approaches to

Q77: Renly, a project manager in a construction

Q84: A project that must be completed by

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines