Multiple Choice
The technique used to help manage the Polaris submarine project and which bases activity estimates on probabilistic estimates of three scenarios is most closely associated with:
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Correct Answer:

Verified
Correct Answer:
Verified