menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project Management Study Set 1
  4. Exam
    Exam 6: The Work Breakdown Structure and Project Estimation
  5. Question
    A Parallel Activity Is a Task That Can Be Worked
Solved

A Parallel Activity Is a Task That Can Be Worked

Question 30

Question 30

True/False

A parallel activity is a task that can be worked on at the same time as another activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q25: Time and effort needed to gather experience

Q26: Under the Precedence Diagramming Method, the situation

Q27: Construct an Activity on the Node (AON)

Q28: The idea that there is a cost

Q29: Under the Precedence Diagramming Method, the most

Q31: What does prorating the cost of a

Q32: Predecessor activities are activities that can be

Q33: The technique used to help manage the

Q34: In the context of critical chain project

Q35: How can parallel activities help shorten the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines