Multiple Choice
Under the Precedence Diagramming Method, the most common relationship between two activities which implies a logical sequence is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q24: What is meant by slack (or float)?
Q25: Time and effort needed to gather experience
Q26: Under the Precedence Diagramming Method, the situation
Q27: Construct an Activity on the Node (AON)
Q28: The idea that there is a cost
Q30: A parallel activity is a task that
Q31: What does prorating the cost of a
Q32: Predecessor activities are activities that can be
Q33: The technique used to help manage the
Q34: In the context of critical chain project