Multiple Choice
Under the Precedence Diagramming Method, the situation which occurs when two activities can start at different times, have different durations, but are planned to be competed at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified
Q21: Installing a server before loading the operating
Q22: PERT was developed in the 1950s to
Q23: _is ensuring that project resources are not
Q24: What is meant by slack (or float)?
Q25: Time and effort needed to gather experience
Q27: Construct an Activity on the Node (AON)
Q28: The idea that there is a cost
Q29: Under the Precedence Diagramming Method, the most
Q30: A parallel activity is a task that
Q31: What does prorating the cost of a