Under the Precedence Diagramming Method, the Situation Which Occurs When

Question 26

Multiple Choice

Under the Precedence Diagramming Method, the situation which occurs when two activities can start at different times, have different durations, but are planned to be competed at the same time is called:


A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these