Multiple Choice
Under the Precedence Diagramming Method, the least common relationship between two activities which occurs when they must complete at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified