Multiple Choice
Based upon the following diagram and activity durations, the Critical Path is:
A) A+B+C+F+H+J
B) A+B+D+F+H+J
C) A+B+D+G+H+J
D) A+B+D+G+I+J
E) A+B+E+G+I+J
Correct Answer:

Verified
Correct Answer:
Verified