menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project Management Study Set 1
  4. Exam
    Exam 6: The Work Breakdown Structure and Project Estimation
  5. Question
    The Technique Used to Find the Sequence of Tasks with Zero
Solved

The Technique Used to Find the Sequence of Tasks with Zero

Question 75

Question 75

Multiple Choice

The technique used to find the sequence of tasks with zero slack (or float) is most closely associated with:


A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q70: Waiting to leave your shift until another

Q71: Under the Precedence Diagramming Method, the situation

Q72: In what ways are project network diagrams

Q73: _ can help manage the Critical Path

Q74: Many organizations have a kick-off meeting because<br>A)

Q76: What is the critical chain? How is

Q77: When does the project manager or team

Q78: Based upon the following diagram and activity

Q79: _ provide valuable information about the logical

Q80: Predecessor activities are activities that must be

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines