Multiple Choice
The technique used to find the sequence of tasks with zero slack (or float) is most closely associated with:
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Correct Answer:

Verified
Correct Answer:
Verified