Multiple Choice
To make a decision to attempt to build an application system based on what was left after a previous attempt ended in failure primarily because of the large investment the company made in the failed project most likely was made by a manager who did not fully understand:
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs