Under the Precedence Diagramming Method, the Situation Which Occurs When

Question 71

Multiple Choice

Under the Precedence Diagramming Method, the situation which occurs when task A cannot end until task B starts is called:


A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these