_____ Can Help Manage the Critical Path by Providing Information

Question 73

Multiple Choice

_____ can help manage the Critical Path by providing information about which activities can be delayed without affecting the deadline target date.


A) Work Breakdown Schedule
B) Gantt Charts
C) PART
D) Project Network Diagrams
E) Critical Path Analysis