Multiple Choice
EV-AC =
A) Cost performance index (CPI)
B) Scheduled performance index (SPI)
C) Cost Variance (CV)
D) Minimum funds needed (MFN)
E) None of these
Correct Answer:

Verified
Correct Answer:
Verified