Having the Team Review the Project Scope, Schedule, Budget, and Quality

Question 79

Multiple Choice

Having the team review the project scope, schedule, budget, and quality objectives would most likely occur in the:


A) Individual Performance Review
B) Postmortem Review
C) Project Audit
D) MOV Evaluation
E) None of these