Multiple Choice
A project selected using the sacred cow model will be maintained until successfully completed or until __________.
A) the project exceeds its budget
B) the project falls behind schedule
C) the boss recognizes the project as a failure and terminates it
D) the project manager is terminated
Correct Answer:

Verified
Correct Answer:
Verified