Multiple Choice
Most heuristic solution methods start with the __________ and analyze resource usage period by period,resource by resource.
A) GERT schedule
B) Gantt chart
C) PERT / CPM schedule
D) Master schedule
Correct Answer:

Verified
Correct Answer:
Verified