Multiple Choice
Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?
A) Each activity will make use of all the slack available to it.
B) The network will not have any critical activities.
C) It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D) Many of the activities will be scheduled prior to the start date of the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q11: In some situations,two activities are scheduled to
Q17: With respect to project scheduling,_ is the
Q21: The use of _ activity time estimates
Q27: Given W = D * U for
Q31: Discuss some other causes of the strong
Q39: In CPM,_ are specified.<br>A)exact levels of uncertainty
Q44: The two fundamental approaches to constrained allocation
Q45: The formula for computing the cost /
Q50: The standard practice with AOA and AON
Q51: If deterministic time estimates are used,and if