Short Answer
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.