Multiple Choice
Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?
A) Start-to-start
B) Finish-to-finish
C) Finish-to-start
D) Start-to-finish
Correct Answer:

Verified
Correct Answer:
Verified