Multiple Choice
Which of the following is a network diagramming technique used primarily to predict total project duration?
A) Gantt chart
B) Critical path analysis
C) Resource breakdown structure
D) Arrow diagramming method
Correct Answer:

Verified
Correct Answer:
Verified