Multiple Choice
_____ includes the processes required to ensure that a project team completes a project within an approved budget.
A) Project scope management
B) Project quality management
C) Project time management
D) Project cost management
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q7: It is important for project managers to
Q37: IT project managers must be able to
Q92: The process of controlling costs primarily involves:<br>A)determining
Q93: A(n) _ is a time-phased budget that
Q93: _ uses project characteristics in a mathematical
Q95: The first step in project cost management
Q96: _ are those costs that are difficult
Q100: The main goal of the _ process
Q101: Which of the following is true of
Q102: A negative schedule variance means that it