Multiple Choice
The main goal of the _____ process is to produce a cost baseline for measuring project performance and project funding requirements.
A) cost budgeting
B) cost planning
C) cost controlling
D) cost estimating
Correct Answer:

Verified
Correct Answer:
Verified