Multiple Choice
Which is a similarity between scope control and schedule control?
A) Both are initial processes of project time management.
B) Both of their primary goals is to define project goals and milestones.
C) Both are portions of the integrated change control process under project integration management.
D) Both of these processes should occur before estimating activity durations.
Correct Answer:

Verified
Correct Answer:
Verified