Multiple Choice
Which of the following contributes to high project risk?
A) Probability of failure is low.
B) If the project fails,the results can be easily rectified.
C) The project is fully insured against failure.
D) Consequences of project failure are serious.
Correct Answer:

Verified
Correct Answer:
Verified