Multiple Choice
Scope creep is ______.
A) a rare occurrence in projects
B) resulted from repeated modifications of a project's specifications
C) resulted from changes in the project's team members
D) always an undesirable development
Correct Answer:

Verified
Correct Answer:
Verified