Multiple Choice
Which of the following is NOT true of activity slack?
A) It is the amount of time an activity may be delayed (from time of early start) without delaying the completion of the project.
B) It is also known as activity float.
C) It is calculated as LS - ES.
D) It is calculated as LF + EF.
Correct Answer:

Verified
Correct Answer:
Verified
Q47: Which of the following is an activity
Q48: Which of the following is NOT a
Q49: A problem with S-curves is that _.<br>A)interpreting
Q50: Which of the following contributes to high
Q51: The numbers in the AOA method represent
Q53: One method for creating an activity network
Q54: To complete a project quickly,we should _.<br>A)crash
Q55: Scope creep is _.<br>A)a rare occurrence in
Q56: The late finish time (LF)is _.<br>A)the latest
Q57: Which of the following correctly pairs the