Early finish time (EF) ______.
A) is the earliest possible date in the year on which an activity can be completed
B) is calculated by adding the duration for an activity to the ES
C) is calculated by subtracting the duration for an activity from the ES
D) is the earliest possible time on a day on which an activity can be completed