Multiple Choice
Which of the following statements is true with regard to the distribution of time for the duration of an activity?
A) The optimistic time estimate is 3 times shorter than the pessimistic time estimate.
B) The most likely time estimate is located at an equidistant interval between the optimistic and pessimistic estimates.
C) The pessimistic and optimistic times are asymmetrical around the mean.
D) The standard deviation for the pessimistic estimate is higher than that for the optimistic estimate.
Correct Answer:

Verified
Correct Answer:
Verified
Q86: Which of the following is not an
Q87: The goal in a project is _.<br>A)to
Q88: Early finish time (EF)_.<br>A)is the earliest possible
Q89: A project's life cycle refers to _.<br>A)the
Q90: In considering the impact supply chains have
Q92: A critical path consists of _.<br>A)activities that
Q93: In comparison to the past,modern weapon systems
Q94: In a Gantt chart,the time to complete
Q95: The projected cost of all of the
Q96: Which of the following is an advantage