Multiple Choice
In a Gantt chart,the time to complete a project can be estimated by ______.
A) the average of the longest duration for each sequenced activity
B) adding the lengths of the longest individual legs of each sequenced activity
C) the average of the longest duration for each sequenced activity multiplied by 3
D) adding the lengths of the shortest individual legs of each sequenced activity
Correct Answer:

Verified