Multiple Choice
Which of the following statements is FALSE with regard to slack time?
A) Slack time is the amount of time an activity can be delayed without delaying the overall project.
B) Slack time is calculated as LF - EF.
C) Slack time is calculated as LS - ES.
D) Slack time is calculated as LF - ES.