Multiple Choice
Item A has a lead time of 2 weeks and requires two units of Item B and three units of Item C.Item B has a lead time of 4 weeks; Item C has a lead time of 1 week.What should the planning horizon of the MRP be?
A) 2 weeks
B) at least 6 weeks
C) always less than 6 weeks
D) 3 weeks
Correct Answer:

Verified
Correct Answer:
Verified