If the Most Optimistic and Pessimistic Times for a Task

Question 3

Multiple Choice

If the most optimistic and pessimistic times for a task are 3 and 11 days respectively,then the variance for the duration of the activity ______.


A) = (3 - 11) / 6) raised to 2
B) = (11 - 3) / 6) raised to 2
C) = (11 - 3) / 3) raised to 2
D) = (3 - 11) / 3) raised to 2

Correct Answer: