Multiple Choice
If the most optimistic and pessimistic times for a task are 3 and 11 days respectively,then the variance for the duration of the activity ______.
A) = (3 - 11) / 6) raised to 2
B) = (11 - 3) / 6) raised to 2
C) = (11 - 3) / 3) raised to 2
D) = (3 - 11) / 3) raised to 2
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: Which of the following does NOT correctly
Q2: If the most optimistic and pessimistic times
Q4: Find the area under the normal curve
Q5: If the standard deviation is 3.4,the Z
Q6: Find the area under the normal curve
Q7: If the standard deviation is 6.5,the Z
Q8: The formula for the variance of the
Q9: If the standard deviation is 4.5,the Z
Q10: If a project has an expected completion
Q11: Whether we should crash an activity or