    If the Most Optimistic and Pessimistic Times for a Task
Solved

If the Most Optimistic and Pessimistic Times for a Task

Question 2

Question 2

Multiple Choice

If the most optimistic and pessimistic times for a task are 3 and 15 days respectively,then the variance for the duration of the activity is ______.


A) 3.00
B) 4.00
C) 5.00
D) 6.00

Correct Answer:

verifed

Verified

Related Questions

Q1: Which of the following does NOT correctly

Q3: If the most optimistic and pessimistic times

Q4: Find the area under the normal curve

Q5: If the standard deviation is 3.4,the Z

Q6: Find the area under the normal curve

Q7: If the standard deviation is 6.5,the Z

Q8: The formula for the variance of the

Q9: If the standard deviation is 4.5,the Z

Q10: If a project has an expected completion

Q11: Whether we should crash an activity or

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines