Multiple Choice
If the most optimistic and pessimistic times for a task are 3 and 15 days respectively,then the variance for the duration of the activity is ______.
A) 3.00
B) 4.00
C) 5.00
D) 6.00
Correct Answer:

Verified
Correct Answer:
Verified