Multiple Choice
If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 18 weeks is ______.
A) less than 34%
B) between 44% and 68%
C) between 69% and 83%
D) more than 93%
Correct Answer:

Verified
Correct Answer: