The Slope for Each Activity Gives ______

Question 31

Multiple Choice

The slope for each activity gives ______.


A) combinations of times and costs for a project's crash options
B) combinations of scheduled and actual times for a project's crash options
C) both A and B
D) neither A nor B

Correct Answer: