If a project is expected to be completed in 68 days with a project variance of 21 days,what due date will give us a 99% likelihood of project completion?


A) in 75 days
B) in 77 days
C) in 79 days
D) in 81 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q22: If project completion times are normally distributed,then

Q23: The proportion of the total budget allocated

Q24: In establishing the project's baseline,the time-phased budget

Q25: Establishing the project's baseline requires _.<br>A)the work

Q26: Find the area under the normal curve

Q28: The SPI is _.<br>A)the stochastic performance index<br>B)the

Q29: If a project is expected to be

Q30: Find the area under the normal curve

Q31: The slope for each activity gives _.<br>A)combinations

Q32: If an activity cannot be shortened,then _.<br>A)the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines