Multiple Choice
If a project is expected to be completed in 68 days with a project variance of 21 days,what due date will give us a 99% likelihood of project completion?
A) in 75 days
B) in 77 days
C) in 79 days
D) in 81 days
Correct Answer:

Verified
Correct Answer:
Verified