If a project is expected to be completed in 68 days with a project variance of 21 days,what is the probability that the project will be completed within 70 days?
A) between 35% and 40%
B) between 45% and 50%
C) between 55% and 60%
D) between 65% and 70%
Correct Answer:

Verified
Correct Answer:
Verified
Q24: In establishing the project's baseline,the time-phased budget
Q25: Establishing the project's baseline requires _.<br>A)the work
Q26: Find the area under the normal curve
Q27: If a project is expected to be
Q28: The SPI is _.<br>A)the stochastic performance index<br>B)the
Q30: Find the area under the normal curve
Q31: The slope for each activity gives _.<br>A)combinations
Q32: If an activity cannot be shortened,then _.<br>A)the
Q33: The normal activity duration of Activity X
Q34: Which of the following statements is true