If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed within 90 days?


A) 85%
B) 90%
C) 95%
D) 100%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: The formula for the variance of the

Q9: If the standard deviation is 4.5,the Z

Q10: If a project has an expected completion

Q11: Whether we should crash an activity or

Q12: Which of the following is NOT one

Q14: If the most optimistic time for completing

Q15: Project overhead costs _.<br>A)are also known as

Q16: The time-phased budget _.<br>A)identifies the correct sequencing

Q17: A project's baseline represents _.<br>A)our best understanding

Q18: If the most optimistic time for completing

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines