menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Managing
  4. Exam
    Exam 4: Supplement: Project Management
  5. Question
    If the Most Optimistic Time for Completing an Activity Is
Solved

If the Most Optimistic Time for Completing an Activity Is

Question 14

Question 14

Multiple Choice

If the most optimistic time for completing an activity is 23,the most likely time is 25,and the most pessimistic time is 39,then the estimated time for the activity is ______.


A) 27
B) 39
C) 42
D) 17

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: If the standard deviation is 4.5,the Z

Q10: If a project has an expected completion

Q11: Whether we should crash an activity or

Q12: Which of the following is NOT one

Q13: If a project is expected to be

Q15: Project overhead costs _.<br>A)are also known as

Q16: The time-phased budget _.<br>A)identifies the correct sequencing

Q17: A project's baseline represents _.<br>A)our best understanding

Q18: If the most optimistic time for completing

Q19: Find the area under the normal curve

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines