Question 79

Multiple Choice

Two hundred fifty units of Component X are scheduled for production.Each unit of X requires labor standard time of 2 hours per unit and machine standard time of 1 hour per unit.The standard machine hours of load requirements are ______.


A) 250
B) 500
C) 400
D) 350