The CRP System Converts Tentative Planned Shop Orders into Standard

Question 76

Multiple Choice

The CRP system converts tentative planned shop orders into standard hours of load by ______.


A) assessing the levels of inventory of finished product,given the availability of raw materials
B) multiplying each period's production quantity requirements by standard labor or equipment requirements per unit,or both
C) averaging the availability of resources per production hour
D) basing the calculations on the production volume from the preceding production period

Correct Answer:

verifed

Verified