Project managers and teams should consider risks and include them in the project charter for all the following reasons EXCEPT:
A) any negative risk that is a threat that may inhibit successful project completion needs to be identified.
B) all project risks should be eliminated before the project charter is signed.
C) a positive risk is an opportunity to complete the project better, faster, and/or at lower cost or to capitalize upon the project in additional ways.
D) sometimes there is more risk to the organization if the project is not undertaken, and this provides additional rationale for doing the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: A project sponsor is wise not to
Q18: During project charter creation there is typically a
Q19: In contrast to a legal contract,the parties
Q20: A well-written business case should persuade decision-makers
Q21: A background statement is a mandatory element
Q23: Which of the following statements accurately describes
Q24: The charter signing represents the transition from
Q25: Risks,assumptions and constraints are included in the
Q26: Which of these charter elements should persuade
Q27: Briefly discuss the importance of the project