    In the Enumeration Method the Project Schedule Is Calculated Many
Solved

In the Enumeration Method the Project Schedule Is Calculated Many

Question 7

Question 7

True/False

In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research

Q3: The most common type of logical dependency

Q4: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System

Q5: All of the following statements correctly describe

Q6: Describe how you would use the members

Q8: A Gantt chart is a horizontal bar

Q9: The amount of time a schedule activity

Q10: A mandatory dependency is a logical relationship

Q11: The schedule activity that determines when the

Q12: The sequencing of activities is often based

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines