True/False
In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q3: The most common type of logical dependency
Q4: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System
Q5: All of the following statements correctly describe
Q6: Describe how you would use the members
Q8: A Gantt chart is a horizontal bar
Q9: The amount of time a schedule activity
Q10: A mandatory dependency is a logical relationship
Q11: The schedule activity that determines when the
Q12: The sequencing of activities is often based