    Exam 8: Scheduling Projects
  5. Question
    The Amount of Time a Schedule Activity Can Be Delayed
Solved

The Amount of Time a Schedule Activity Can Be Delayed

Question 9

Question 9

Multiple Choice

The amount of time a schedule activity can be delayed without delaying the early start date of immediately following schedule activities is:​ 


A)  reserve 
B)  free float 
C)  contingency 
D)  lead

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System

Q5: All of the following statements correctly describe

Q6: Describe how you would use the members

Q7: In the enumeration method the project schedule

Q8: A Gantt chart is a horizontal bar

Q10: A mandatory dependency is a logical relationship

Q11: The schedule activity that determines when the

Q12: The sequencing of activities is often based

Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-5 Duration

Q14: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines