Question 41
Multiple Choice
Which of these is NOT one of the items that can provide useful assistance to a project team to define the activities of a project?
Question 42
Multiple Choice
Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?
Question 43
Multiple Choice
Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?
Question 44
Multiple Choice
Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?
Question 45
Multiple Choice
Figure 7-6 Network Scheduling Data -Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?
Question 46
True/False
Even small delays on "near-critical" activities can change the critical path of a project.
Question 47
True/False
A successor activity is the schedule activity that follows a predecessor activity,as determined by their logical relationship.
Question 48
True/False
The length of time to perform an activity is often dependent upon who will do that work.
Question 49
Multiple Choice
Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?
Question 50
Multiple Choice
Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C) ,without impacting the expected project completion date?
Question 51
True/False
When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.
Question 52
Multiple Choice
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT: