Multiple Choice
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?
A) 0
B) 15
C) 80
D) 107
Correct Answer:

Verified
Correct Answer:
Verified