All of the following describe an appropriate application of Plan Risk Responses in project management EXCEPT:
A) Risk response planning should address both opportunities and threats.
B) Responses should be created for every identified project risk, regardless of the risk score.
C) The expectations of the sponsor and key stakeholders should influence the risk responses that are developed.
D) Often multiple strategies are identified for a single risk.
Correct Answer:

Verified
Correct Answer:
Verified
Q18: All of the following describe the appropriate
Q19: A risk management plan should define who
Q20: Which of the following quantitative risk analysis
Q21: A _ presents a hierarchical organization of
Q22: Which of the following describes the activities
Q24: Which of the following activities illustrates a
Q25: The process of defining how to conduct
Q26: Which of the following activities illustrates a
Q27: When complete,the risk register presents the results
Q28: Once risks have been identified and analyzed,the