Multiple Choice
Which of the following quantitative risk analysis techniques is used to determine which risks have the most powerful impact on the project,with results displayed in the form of a tornado diagram?
A) Failure Mode and Effects Analysis (FMEA)
B) Expected Monetary Value (EMV)
C) Sensitivity Analysis
D) Simulation Techniques such as Monte Carlo Analysis
Correct Answer:

Verified
Correct Answer:
Verified